Case Study: Contract Administration for the Project Alpha, KSA

Case Study: Contract Administration for the Project Alpha, KSA

Background:

The Project Alpha in the Kingdom of Saudi Arabia (KSA) is a high-profile initiative of strategic importance, valued in circa US$ 2.4 billion. Project details cannot be disclosed due to confidentiality reasons. The CLIENT awarded the project to the CONTRACTOR, with a project timeline of 3 years. The CLIENT also employed a CONSULTANT as its Project Management Consultant (CONSULTANT) to oversee project delivery.

The contractual agreement was highly one-sided, favouring the CLIENT, with strict terms and limited execution freedom for the CONTRACTOR. Furthermore, the CONSULTANT adopted a inflexible and contractual approach throughout, often issuing instructions and communications that were strictly aligned with the contract, with little flexibility for practical challenges. This led to significant delays, financial strain, and potential exposure to liabilities for the CONTRACTOR.

To mitigate these risks, Petrocontracts was engaged to provide contract administration services and defend the CONTRACTOR’s commercial and contractual interests.

Challenges Faced

1. Onerous Contractual Terms:

  • The contract imposed stringent obligations on the CONTRACTOR without provisions for practical adjustments. Clauses heavily favoured CLIENT, such as unilateral change orders and punitive damages for delays.

2. CONSULTANT’s Strict Approach:

  • CONSULTANT maintained a "bookish" interpretation of the contract, often ignoring on-ground realities and adopting a position of intransigence. Communications were highly formal and contractual, limiting collaboration and practical problem-solving, delays and numerous iterations of approvals became a theme throughout the lifecycle of the Consultants engagement.

3. Financial Impact:

  • Delays caused by impractical demands and inflexibility severely impacted not only the CONTRACTOR’s cash flow it placed strain on the Subcontractors financial positions and increased project costs. Liquidated damages (LDs) and additional liability risks further burdened the CONTRACTOR.

4. Slow Progress:

  • Excessive procedural requirements, delayed approvals, and frequent disputes over minor issues impeded progress, exposing the CONTRACTOR to potential contractual penalties and reputational damage.

Actions Taken by Petrocontracts

1. Proactive Contractual Review and Strategy Development

  • Conducted a detailed review of the contract to identify ambiguities and leverage points as enablers in discussions and strategy planning.
  • Developed a risk matrix highlighting areas where the CLIENT and CONSULTANT were failing to meet their obligations (e.g., timely approvals, clarity in instructions).
  • Established a claims strategy to address delays caused by CLIENT and CONSULTANT, supported by contemporaneous evidence.

2. Improved Communication and Documentation

  • Implemented a structured communication process to ensure all instructions, variations, and delays were documented in a manner defensible in disputes.
  • Responded to CONSULTANT’s contractual communications with detailed counterarguments and rebuttals supported by contract clauses and factual evidence.

3. Mitigating Delays and LD Risks

  • Advocated for extension-of-time (EOT) claims by presenting detailed delay analyses using tools such as the critical path method (CPM).
  • Highlighted and articulated the CLIENT and CONSULTANT’s contributions to delays (e.g., late approvals, unclear specifications).
  • Ensured that all change orders were formally acknowledged, preventing the CONTRACTOR from absorbing unauthorized costs.

4. Cost Recovery Measures

  • Prepared comprehensive cost claims for additional expenses incurred due to CLIENT and CONSULTANT’s inflexible approach, including disruption and prolongation costs.
  • Identified opportunities for claiming compensation for variations and rework caused by unclear instructions from CONSULTANT.

4. Stakeholder Negotiation

  • Recommended the CONTRACTOR to engage in high-level discussions with CLIENT to emphasize the risks of project failure and cost escalation due to CONSULTANT’s inflexibility.
  • Advocated for practical solutions, including collaborative problem-solving sessions and expedited approval processes.

Outcomes and Key Achievements

1. Extension of Time (EOT):

  • Petrocontracts successfully negotiated an EOT of x months, avoiding penalties and mitigating the CONTRACTOR’s liability for delays.

2. Cost Recovery:

  • Prepared and submitted claims totalling USD xxxx million, of which USD xxx million was considered as compensable, significantly easing the CONTRACTOR’s financial strain.

3. Improved Communication Channels:

  • Introduced regular tri-party meetings (CONTRACTOR, CONSULTANT, CLIENT) to address project challenges collaboratively, reducing contractual friction.

4. Risk Mitigation:

  • Proactively highlighted contractual risks to the CONTRACTOR, ensuring all potential exposures were documented and addressed in real time.

4. Stakeholder Engagement:

  • Continuously influenced CLIENT to adopt a more flexible approach by presenting the long-term risks of project delays and cost overruns.

Lessons Learned

1. Early Identification of Contractual Risks:

  • Reviewing contract terms during the tendering phase is crucial to anticipate challenges and negotiate balanced conditions.

2. Importance of Documentation:

  • Maintaining detailed records of instructions, delays, and costs is essential for defending claims.

3. Collaborative Problem-Solving:

  • Encouraging open communication between stakeholders can mitigate rigid interpretations of contractual terms.

4. Professional Support:

  • Engaging a skilled contract administration team can protect contractors’ commercial interests and ensure fair treatment under challenging conditions.

Conclusion

The Project Alpha demonstrated the importance of proactive contract management in navigating one-sided contracts and inflexible project management practices. Petrocontracts played a pivotal role in defending the CONTRACTOR’s commercial interests, ensuring fair compensation, and mitigating risks, enabling the project to move toward successful completion.

Due to confidentiality agreements and professional discretion, we will refer to the project as 'Project Alpha' and the entities involved as 'Client,' 'Contractor,' and 'Consultant' for the purposes of this case study."

Petrocontracts possesses the necessary skills and resources to effectively manage its offered services in the energy sector ranging from simple to complex projects. Petrocontracts will be pleased to provide a more accurate assessment, additional information about Petrocontracts' specific expertise, experience in providing its services, and available resources. Please contact us at [email protected] and one of our senior representatives will get in touch with you.

Expert

·  Dispute expert witnesses

·  Expert advisory

Project Management Services

Proposal & Estimation Services

·  Construction Cost Management

Contracts & Sub-Contracts Management

Claims Management

·  COVID 19 Claim Management

·  Claims Preparation & Defense

·  Dispute Avoidance & Resolution

·  Forensic Planning

Engineering Services

Business Representation

Resource Management

Durg Manglam Projects Pvt. Ltd

ConSca